Inside NEOM’s Green Hydrogen Plant: Final EPC Push and Electrolyser Installations Before Startup
/ Insights / Articles / Inside NEOM’s Green Hydrogen Plant: Final EPC Push and Electrolyser Installations Before Startup

Inside NEOM’s Green Hydrogen Plant: Final EPC Push and Electrolyser Installations Before Startup

Published on: Sep 02, 2026 | Author: Marketing & Communications

NEOM’s flagship green hydrogen and ammonia complex at Oxagon is being developed by NEOM Green Hydrogen Company (NGHC), a joint venture involving NEOM, Air Products, and ACWA Power. The project is positioned by the developer and multiple reports as a landmark in large-scale, renewables-based hydrogen production and export. The facility is planned to produce up to 600 tonnes of carbon-free hydrogen per day and convert it into green ammonia for global export. Reported project figures include approximately 4 GW of renewable hydrogen via electrolysis and a target of 1.2 million tonnes of ammonia annually, alongside an estimate of avoiding about 5 million tonnes of CO2 emissions per year.

Across updates, the build has been described as approaching its final stretch. A June 2025 announcement cited 80% construction completion across all sites, including the hydrogen facility, wind garden, solar farm, and transmission grid. By early 2026, several outlets reported construction as 90% complete across the integrated scope, again covering the hydrogen production facility, renewables, and grid. In parallel, NGHC has said its renewable power generation assets—wind farm, solar installation, and the transmission grid—reached about 95% completion as of a March update cited by Energy Intelligence. These numbers frame the near-finish EPC picture across multiple workfronts rather than a single unit.

What the Late-Stage EPC Scope Includes at Oxagon

The NEOM green hydrogen plant construction EPC effort has been structured to deliver an integrated system: power generation, transmission, and the hydrogen-and-ammonia process units. Air Products was awarded the main EPC contract, and L&T (Larsen & Toubro) received a sub-EPC contract during the first phase that began in Q2 2020. The project is described as being built in multiple phases. As construction progressed, milestone equipment was reported as received and installed by June 2025, including electrolysers, hydrogen storage tanks, and pipe racks. The plant sits at Oxagon and is described as covering an area of 300 km² within the NEOM megacity.

Cost and financing details also define how the build is being executed. One report lists the project cost at USD 8.4 billion, while another cites USD 8.5 billion. Funding is described as coming from local, regional, and international banks, including a figure of 23 banks and financial institutions in one source. The project reached financial close on May 22, 2023, when an exclusive 30-year offtake agreement for the green ammonia produced was signed. Reports also characterize this moment as a major step for gigawatt-scale green hydrogen developments, enabling accelerated procurement and on-site execution.

Read also Building King Salman International Stadium: A Clear Delivery Timeline for Riyadh’s 2034 World Cup Final Venue (King Salman Stadium Construction Riyadh 2026)

Commissioning and delivery timing is discussed as a sequence rather than a single date. IndexBox reports that ACWA Power and Air Products have finished construction and that the facility has entered the commissioning phase, citing a senior official and comments made on an earnings call. Separately, NGHC updates point to up to 4 GW of combined solar and wind power capacity targeted for completion by mid-2026, followed by commissioning of electrolysers and first green ammonia output planned for 2027. This positions the remaining work as integration, commissioning, and staged start-up across renewable generation and process units, with product availability expected in 2027.

Who is building NEOM’s green hydrogen project at Oxagon?

The project is run by NEOM Green Hydrogen Company (NGHC), a joint venture involving NEOM, Air Products, and ACWA Power.

What is the reported construction progress across the NEOM hydrogen facility, renewables, and grid?

Multiple reports state construction reached 90% completion across all sites, including the hydrogen production facility, wind garden, solar farm, and transmission grid. A June 2025 update had cited 80% completion across those sites.

What is the planned output of the NEOM facility once operational?

The facility is expected to produce up to 600 tonnes of carbon-free hydrogen per day, which will be converted into green ammonia for global export. Reported targets also include 1.2 million tonnes of ammonia annually.

How does the NEOM green hydrogen plant construction EPC scope link to commissioning timelines?

Reports describe renewables and grid completion tracking toward mid-2026, with commissioning of electrolysers and the first green ammonia output planned for 2027. IndexBox also reports the overall facility has entered the commissioning phase.

What project cost and offtake details have been reported for NEOM’s green hydrogen complex?

Sources cite a project cost of USD 8.4 billion and USD 8.5 billion. An exclusive 30-year offtake agreement for the green ammonia produced was signed at financial close on May 22, 2023.

Ready to Build Your Construction Growth in Saudi Arabia?

We help construction companies, developers, investors, and project partners turn market opportunities into practical strategies, stronger delivery models, and long-term growth.

Contact Us Today
Contact Us Today

/ Contact Us

Let’s discuss how we can support your construction strategy in Saudi Arabia.

 

  • No results found

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.